Home › New York City, NY › Permit
HVAC permit at 435 HUDSON STREET, Manhattan
HVACRemodeling
Contractor on record: CLUNE CONSTRUCTION CO LP
Named on this permit by NYC Open Data (DOB NOW) · 131 permits tracked since 2026-07-27 · $99,556,799 total declared value.
View full contractor profile →Work description
Modifications to existing HVAC System: Remove, relocate and reinstall exiting ductwork and infrastructure to accommodate interior renovations on the Cellar and 1st Floor as per plans (Hines Storefront Phase 2.) No change in use, egress or occupancy.
More from CLUNE CONSTRUCTION CO LP
| Issued | Address | Work description | Est. value | |
|---|---|---|---|---|
| 2026-11-17 | 1372 BROADWAY, Manhattan · 10018 | STRUCTURAL MODIFICATIONS TAKING PLACE ON CEL, 1ST & 14TH (ROOF BULKHEAD) AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY, RoofingFoundation | $275,000 | › |
| 2026-11-16 | 600 LEXINGTON AVENUE, Manhattan · 10022 | Filing herewith drawings indicating modification of the Mechanical system on the 12th floor. No change in use, egress, or occupancy under this application. HVAC | $361,494 | › |
| 2026-11-12 | 1 PENN PLAZA, Manhattan · 10119 | Mechanical work on the 53rd floor (prebuild) as indicated on drawings. HVAC | $31,985 | › |
| 2026-11-12 | 90 PARK AVENUE, Manhattan · 10016 | Architectural changes on the 26th floor as indicated on drawings. | $1,207,018 | › |
| 2026-11-10 | 605 THIRD AVENUE, Manhattan · 10158 | General Construction to take place on the 4th Construction floor as per drawings filed herewith. No change in use, egress, or occupancy. | $321,000 | › |
Property history
| Issued | Address | Work description | Est. value | |
|---|---|---|---|---|
| 2026-11-06 | 435 HUDSON STREET, Manhattan · 10014 | inspection using industrial rope access techniques and methods. See attached plans designated primary site supervisor: Brian Barco | — | › |
| 2026-10-21 | 435 HUDSON STREET, Manhattan · 10014 | Provide metered domestic water to work area; install piping on the Cellar and 1st Floor as per plans (Hines - Storefront Phase 2.) No change in use, egress or occupancy. Plumbing | $35,000 | › |
| 2026-10-21 | 435 HUDSON STREET, Manhattan · 10014 | Relocate (10) existing sprinkler heads and associated piping to accommodate lower slab height on the Cellar Level as per plans (Hines Storefront - Phase 2.) No change to use, egres | $12,000 | › |
| 2026-10-07 | 435 HUDSON STREET, Manhattan · 10014 | Filing for installation of mechanical units for restaurant space on the first floor, in association with general construction application # M01213438-I1. HVAC | $255,000 | › |
| 2026-09-29 | 435 HUDSON STREET, Manhattan · 10014 | Structural modifications: Recessing two bays of slab at the 1st Floor to accommodate a stair and an ADA ramp on the 1st Floor as per plans (Hines - Storefront Phase 2.) No change t Foundation | $150,000 | › |
| 2026-08-13 | 435 HUDSON STREET, Manhattan · 10014 | Minor interior demolition; Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 7th floor as per plans (Hines - Demo, Whitebox & Stair I Demolition | $217,389 | › |
| 2026-08-13 | 435 HUDSON STREET, Manhattan · 10014 | Minor interior construction, patching and repair of finishes in tenant spaces on the Cellar-9th and Roof as per plans (Hines Fire Alarm System Upgrade.) No change to use, egress or Roofing | $400,000 | › |
| 2026-08-13 | 435 HUDSON STREET, Manhattan · 10014 | Minor demolition. Installation of new exterior storefront, windows, exterior door, interior stair and ADA access ramp on the Cellar and 1st floors as per plans (Storefront Phase 2. DemolitionWindows & Doors | $583,000 | › |
| 2026-08-12 | 435 HUDSON STREET, Manhattan · 10014 | Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 7th Floor and Reinstall ductwork on the 6th Floor in relation to slab in HVACDemolition | $6,426 | › |
| 2026-08-12 | 435 HUDSON STREET, Manhattan · 10014 | Minor interior demolition, removal of interior non-load bearing partitions and finishes on the 1, 2, 5th and Roof as per plans (Hines Demo & Whitebox.) No change to use, egress or RoofingDemolition | $599,926 | › |
| 2026-08-12 | 435 HUDSON STREET, Manhattan · 10014 | Modifications to existing HVAC System: Remove ductwork, diffusers, AC units and associated equipment on the 1, 2, 5, 8, Roof as per plans (Demo & Whitebox.) No change in use, egres RoofingHVACDemolition | $26,853 | › |
| 2026-07-31 | 435 HUDSON STREET, Manhattan · 10014 | INSTALLATION OF TEMPORARY CONSTRUCTION PLYWOOD FENCE AS PER PLANS DURING CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE SHALL COMPLY WITH CHAPTER 33 OF NYC BUILDING COD Fencing | $31,000 | › |
Public record from NYC Open Data (DOB NOW). Owner name and contact details are not part of this open-data feed unless shown above. Verify details before use.
Get these leads in your inbox — free
One email a week with the newest permits for your trade and area. Tell us what you cover and we'll filter it for you. Unsubscribe anytime.