Work description
Interior/Exterior Work Electrical Infrastructure Upgrade of the Jimmy Fund Research Building. Consists of new structure at current Loading dock to support new Emergency Electrical Room and Generator Platform along with retrofit of main substation. Includes new structure, facade, enclosure, finishes, and support MEPF.
Property history
| Issued | Address | Work description | Est. value | |
|---|---|---|---|---|
| 2026-10-29 | 35 Binney ST Boston · 02115 | Plumbing New plumbing rough piping & fixtures for DFCI Proton Therapy Suite Plumbing | $350,000 | › |
| 2026-10-02 | 35 Binney ST Boston · 02115 | Generators Install 750 KW Roll up generator for a duration of 10 Months for installation of new structure for new generator Electrical | $110,000 | › |
| 2026-09-24 | 35 Binney ST Boston · 02115 | Electrical New Infrastructure upgrades to accommodate new Proton equipment being installed under separate project Electrical | $4,220,000 | › |
| 2026-08-13 | 35 Binney ST Boston · 02115 | Renovations - Interior NSC Renovation of the Jimmy Fund Auditorium to repurpose for use as a Proton Therapy Treatment Center and Supporting Clinic. Will include new Proton Therapy Remodeling | $16,717,860 | › |
| 2026-08-03 | 35 Binney ST Boston · 02115 | Electrical Renovation of auditorium space to a Proton therapy suite ElectricalRemodeling | $1,750,000 | › |
| 2026-08-03 | 35 Binney ST Boston · 02115 | Fire Alarm Renovation of old auditorium to a proton therapy suite ElectricalRemodeling | $125,000 | › |
| 2026-07-15 | 35 Binney ST Boston · 02115 | Temporary Service Install temp 1200 amp 480 volt switchboard , 800 amp 208 volt switchboard to accommodate retro fit of existing main switchgear Electrical | $125,000 | › |
| 2026-07-13 | 35 Binney ST Boston · 02115 | Electrical New Infrastructure upgrades to accommodate new Proton equipment being installed under separate project Electrical | $4,220,000 | › |
| 2026-07-13 | 35 Binney ST Boston · 02115 | Fire Alarm New Fire alarm devices to support new 750 KW generator and housing being placed Electrical | $110,000 | › |
Public record from Analyze Boston (City of Boston Open Data). Owner name and contact details are not part of this open-data feed unless shown above. Verify details before use.
Get these leads in your inbox — free
One email a week with the newest permits for your trade and area. Tell us what you cover and we'll filter it for you. Unsubscribe anytime.